The Dholera Ultra-Mega Solar Power Park is a phased renewable-energy project inside the Dholera Special Investment Region, approved around April 2018. Its ultimate announced target is 5,000 MW, or 5 GW, by roughly 2030, but that figure is a goal, not installed capacity. The durable, sourced position in 2026 is about 300 MW commissioned, including a 300 MW Tata Power plant, with a 1,000 MW Phase-I sanctioned under Gujarat Power Corporation Ltd. A further 700 MW is under development, targeted for March 2027 and awarded to ReNew, SJVN, Vena and TEQ Green, though tariff and regulatory disputes have caused delays. So Dholera is a real clean-power hub today, at a fraction of its long-range ambition.
The Dholera Ultra-Mega Solar Power Park is one of the two industrial anchors in the Dholera Special Investment Region that has genuinely moved from paper to power, alongside the Tata semiconductor fab. It is easy to find the headline number, 5,000 MW, repeated everywhere. It is harder to find an honest read of how much of that is actually generating electricity today. This page separates the durable, commissioned capacity from the sanctioned pipeline and the long-range target, using dated figures only. Where a number is a goal rather than a done deal, it is flagged plainly.
The short answer
About 300 MW of solar is commissioned and live at Dholera. A 1,000 MW Phase-I has been sanctioned through Gujarat Power Corporation Ltd, and the ultimate announced target is 5,000 MW, or 5 GW, by roughly 2030. That 5,000 MW figure is the ambition for the full park, not installed capacity, so it should never be quoted as if the park already produces that much. The realistic 2026 picture is a working solar hub of a few hundred megawatts, with a much larger pipeline still under development.
Who is building it
The park was approved around April 2018 and is coordinated through Gujarat Power Corporation Ltd, or GPCL, the state agency acting as nodal developer for Phase-I. The most concrete piece on the ground is a 300 MW plant commissioned by Tata Power. Tata Power reports it uses 873,012 monocrystalline modules across about 1,320 acres and calls it India's largest single-axis solar tracker installation. That is a real, operational asset, and it is the reason Dholera can honestly claim live clean-power capacity rather than only a plan.
For Phase-I, the Central Electricity Authority's quarterly solar-parks report, as on September 2025, records 1,000 MW sanctioned with GPCL as agency, roughly 300 MW commissioned, and about 700 MW under development targeted for March 2027. That 700 MW has been awarded across several developers: ReNew, SJVN, Vena and TEQ Green, with Tata Power also named in the awarded set. These are established renewable players, which strengthens the pipeline's credibility even though the capacity is not yet built.
Capacity roadmap: what is live, sanctioned, and targeted
The clearest way to hold the numbers is a three-tier ladder. The bottom rung is commissioned capacity you can count today. The middle rung is sanctioned Phase-I capacity with agencies and awards attached. The top rung is the promotional ultimate target, which is real as an ambition but not as generation. Keeping these separate is the difference between an accurate statement and a marketing one.
| Tier | Capacity | Status |
|---|---|---|
| Commissioned | ~300 MW | Durable, live (incl. Tata Power 300 MW plant) |
| Phase-I sanctioned | 1,000 MW | Reported, CEA Sept 2025 (GPCL agency) |
| Under development | 700 MW | Target March 2027 (ReNew, SJVN, Vena, TEQ Green) |
| Ultimate target | 5,000 MW | Target by ~2030, not installed |
| Park approval | ~April 2018 | Durable |
Why the solar park matters to the whole region
The solar park is not a stand-alone green statement. It is part of the industrial logic of the region. A semiconductor fab and other advanced manufacturing need enormous, uninterrupted, clean power, and the presence of a large solar base near the industrial zones helps make that case. The park also gives Dholera a second bankable anchor beyond the fab, which matters for a greenfield city trying to prove it can deliver at scale rather than only announce.
- Powers the industrial base: clean generation sits close to the manufacturing zones, part of why the semiconductor fab and the region's energy planning are read together.
- A second proven anchor: alongside the fab, live solar capacity is evidence the region delivers infrastructure, not only master plans.
- Credible developers: Tata Power, ReNew, SJVN, Vena and TEQ Green are named across the commissioned and pipeline capacity.
- Land and sunlight fit: flat, low-lying coastal land near the Gulf of Khambhat suits large single-axis tracker arrays.
Delays and the honest caveats
The pipeline has not moved on a straight line. The 700 MW under development has been slowed by tariff and regulatory disputes, including matters before the Gujarat Electricity Regulatory Commission (GERC). That is a normal feature of large solar procurement in India, where the price at which power is sold has to clear regulatory review, but it means the March 2027 target for that tranche is a target and can move. The gap between the 5,000 MW ambition and the roughly 300 MW live today is the single most important thing to keep in view: the park is real and working, at a small fraction of its eventual promise.

Frequently asked questions
How much solar is actually operational at Dholera?
What is the Dholera solar park's total planned capacity?
Who is developing the Dholera solar park?
When was the Dholera solar park approved?
Why is the pipeline behind schedule?
Dholera 2047. (2026). Dholera Solar Park: Capacity, Anchors, and What Is Actually Live. Retrieved 23 July 2026, from https://dholera2047.com/dholera-solar-park.htmlSources & references
- Dholera 2047 Fact Pack (verified July 2026)
- Central Electricity Authority, quarterly solar-parks report, as on September 2025 (Phase-I 1,000 MW sanctioned, ~300 MW commissioned, 700 MW under development)
- Tata Power / tatapowersolar.com (300 MW Dholera plant, single-axis tracker)
- Gujarat Power Corporation Ltd (GPCL, Phase-I nodal agency)
- Wikipedia, Dholera Solar Park (park overview, 5,000 MW target)
Dholera 2047 labels facts by confidence. Figures marked reported or target come from press or announcements and may change; verify anything time sensitive against the official source before acting.