Dholera milestones from 2028 to 2042, by target date, and what the record says about 2047
Updated 11 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.
Eight Dholera milestones carry a stated target date between 2028 and 2042: a data centre and an aircraft assembly plan around 2028, Tata fab commercial production around mid-2028, a state data centre target for 2029, solar at 5,000 MW around 2030, rail by 2030-31, Phase II by 2032 and full build-out around 2040 to 2042. No document in our record sets a Dholera milestone for 2047.
Eight milestones, earliest first
| Order | Target date | Milestone | Who stated it | Kind of source |
|---|---|---|---|---|
| 1 | Around 2028 | L&T Vyoma AI data centre in Dholera, 250 MW stated; reports differ on 2028 (operational by 2028 in some, proposed start of development in DeshGujarat) | Agreement, reported by All India Radio on 20 February 2026 | Government news item |
| 2 | Around 2028 | Final assembly line for civil aircraft at Dholera airport, Embraer and Adani signed a memorandum in January 2026; Dholera was reported as the site in June 2026 and the companies have not confirmed it | Memorandum of January 2026; Dholera reported as the site in June 2026 | Reported, memorandum stage |
| 3 | Mid-2028 | Tata fab begins commercial production | Ministry statement and company comment, reported in July 2026 | Reported by trade press |
| 4 | By 2029 | Gujarat target of 7.5 GW of green AI data centre capacity, with Dholera a preferred location | Viksit Gujarat Data Centre Policy 2026-29, notified 7 August 2026 | Reported by a news agency; a state-wide target |
| 5 | Around 2030 | Solar park reaches its 5,000 MW long-range target | Solar park plan; 1,000 MW sanctioned in Phase I | Target, official |
| 6 | Up to 2030-31 | Ahmedabad-Dholera semi-high-speed rail completed | Union Cabinet release of 13 May 2026 | Government release (PIB) |
| 7 | 2032 | Phase II planning period ends (schemes TP3 and TP4, 126 sq km) | Sanctioned Development Plan profile | Government plan |
| 8 | About 2040 to 2042 | Full build-out of Phase III and the plan, with about 800,000 jobs and a reported promotional figure of about 1 million residents as targets | Development Plan for the phases and jobs; the population figure is a reported promotional target and published figures vary | Government plan; end year stated as 2040 or 2042 |
1. Tata fab begins commercial production
- TargetMid-2028, reported
- InvestmentAbout Rs 91,000 crore
The fab is the anchor of the semiconductor plan. A July 2026 report said commercial output is expected around mid-2028 and mostly on a 90 nm process at launch. The company has said its plan spans 28 to 110 nm.
2. Ahmedabad-Dholera semi-high-speed rail completed
- Length134 km
- CostAbout Rs 20,667 crore
- LinksAhmedabad, Dholera SIR, the airport and Lothal
The Cabinet release states cost, length and the 2030-31 target. No tender or construction start has been reported as of 11 November 2026.
3. Full build-out of Phase III and the plan
- Phase III2033 to 2042, TP5 and TP6, 142 sq km
- Population targetAbout 1 million, reported promotional target; sources vary
- Jobs targetAbout 800,000
Sources state the end year of the full plan as both 2040 and 2042, so this page gives the range. The 2020 targets of about 120,000 residents and 80,000 jobs for the first phase have lapsed.
4. Solar park reaches its 5,000 MW long-range target
- CommissionedAbout 300 MW at 30 June 2026
- Sanctioned Phase I1,000 MW
5,000 MW is the ultimate announced target. It is not capacity in operation.
What the record says about 2047
The year 2047 is the centenary of independence, and it is often used as a planning horizon in India. No Dholera plan, release or agreement in our record gives a milestone for 2047. The plan itself runs to about 2040 to 2042. So there is no dated Dholera milestone for 2047 in the record, and this page does not invent one.
How to read target dates
Dholera's own record shows how targets move. The airport was first aimed at December 2025, then September to October 2026, then the end of 2026. The first-phase population targets for 2020 lapsed. A milestone here is the newest date a source has stated.
Using the list for your own plan
- Pick the milestone that matters most to your plot, such as rail or the fab.
- Ask what you would do if it arrived two or three years late.
- Check the GujRERA registration, title and price of the exact plot before you pay.
What this list cannot tell you
This list collects target dates that public sources have stated. It cannot say that any date will be met, and it says nothing about what a plot will be worth.
Questions people ask
What will Dholera look like in 2047?
No document in our record sets a Dholera milestone for 2047. The plan runs to about 2040 to 2042, with about 800,000 jobs and a reported promotional figure of about 1 million residents as targets. Treat any 2047 picture as an extension of those targets.
When will Dholera be fully built?
The plan targets full build-out around 2040 to 2042. Sources give both years. Phase II is listed for 2023 to 2032 and Phase III for 2033 to 2042. These are planning periods, and some earlier targets have already moved.
When will the Dholera semi-high-speed rail be ready?
The Union Cabinet release of 13 May 2026 targets completion up to 2030-31 for the 134 km line, at about Rs 20,667 crore. No construction start has been reported as of 11 November 2026.
When will the Dholera solar park reach 5,000 MW?
5,000 MW is a long-range target for around 2030. About 300 MW was commissioned at 30 June 2026 out of 1,000 MW sanctioned for Phase I. No newer operating figure has been found.
Read next
- Dholera timeline and phases explained
- Dholera completion date
- Dholera population and jobs projection
- Dholera data centre hub
Sources
- All India Radio: L&T Vyoma data centre agreement in Dholera (20 February 2026)
- IANS: Gujarat notifies data centre policy (7 August 2026)
- Press Information Bureau: Cabinet approves Ahmedabad-Dholera semi-high-speed rail (13 May 2026)
- TrendForce: Tata fab reportedly to launch at 90nm, commercial production mid-2028 (20 July 2026)
- DSIRDA sanctioned Development Plan profile (checked November 2026)