Dholera smart city completion date: what the plan says, and which targets have moved
Updated 11 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.
There is no single completion date for Dholera. The sanctioned development plan builds the region in three phases to 2042, though end-years are quoted as 2040 or 2042 in different reports. As of 12 November 2026 the expressway is open, the airport is expected by the end of 2026, the chip fab targets mid-2028 and the rail line has a reported target of 2030-31.
Dholera targets and where each stands
| Item | Stated target | Status as of 12 November 2026 | Source and date |
|---|---|---|---|
| Phase I: TP1 and TP2 (about 153 sq km) | Reported 2020 to 2025 | Activation Area (about 22.5 sq km) is where the first roads and utilities were built; the wider phase is not complete | DSIRDA sanctioned Development Plan; reported targets |
| Phase II: TP3 and TP4 (126 sq km) | 2023 to 2032 | Plan period only; no completion reported | DSIRDA sanctioned Development Plan |
| Phase III: TP5 and TP6 (142 sq km) | 2033 to 2042 | Plan period only; no completion reported | DSIRDA sanctioned Development Plan |
| Ahmedabad-Dholera Expressway | Opening | Inaugurated on 31 March 2026 | Government and press coverage, March 2026 |
| Dholera International Airport | Earlier targets: 2024, March 2026, September or October 2026 | Not open. Expected operational by end of 2026 (Chief Minister's review, 16 October 2026). No licence or airline schedule reported | NewKerala, 16 October 2026 |
| Tata Electronics-PSMC chip fab | Commercial production mid-2028 | Under construction. No percentage complete is printed here | TrendForce, 20 July 2026 |
| Semi-high-speed rail, 134 km | Reported 2030-31 | Cabinet approved 13 May 2026 (Rs 20,667 crore). A tender was reported in August 2026. No construction start reported | ThePrint, 13 May 2026; India Shipping News, 3 August 2026 |
| Raw water reservoir, 2,200 million litres | 18-month build once started | Announced at Rs 438.74 crore. Bids not stated in the report | DeshGujarat, 3 November 2026 |
Why there is no one date
Dholera is not one building. It is a region of about 920 sq km, divided into six town planning schemes, with roads, utilities, factories, an airport and housing arriving at different times. The sanctioned Development Plan splits it into three phases. Phase I covers Town Planning Schemes 1 and 2, Phase II covers 3 and 4, and Phase III covers 5 and 6. The three phase areas add up to about 421 sq km, close to the 422 sq km the six schemes cover.
The plan period for the last phase ends in 2042. Some reports give 2040, so treat the end-year as a reported range and not as a promise.
Targets that have moved
The airport is the clearest case. Earlier targets of 2024 and March 2026 passed. In July 2026 the ministry said it aimed to be operational within three months. On 16 October 2026 the Chief Minister was told it is expected by the end of 2026. The first trial landing was on 4 June 2026, and AAI and the airport company reportedly signed an operation agreement about 4 November 2026. A calibration flight has been reported without a date.
Our page on milestones from 2028 to 2042 sets the longer dates side by side.
How to read a target
- A government release or a company release is firmer than a single local news item.
- A target is a date someone hopes to meet. It becomes a fact when the thing opens.
- A project being under construction does not mean it will finish by the date in a brochure.
What a buyer should take from this
If your plan depends on a date, such as moving in, renting out or reselling, build in a margin of years. Past airport targets passed without opening. Ask any seller to put the dates they quote into the signed agreement, with refund terms if they are missed. The refund and cancellation rights page explains what to look for.
What we do not know
The record we hold does not state a date for completion of Phase I, a percentage complete for the fab, or an opening date for the rail line. Those are written here as not stated.
Questions people ask
When will Dholera smart city be completed?
No single date is published. The sanctioned plan builds the region in three phases to 2042, and some reports say 2040. Project dates differ: airport expected by end of 2026, chip fab mid-2028, rail reported 2030-31. All are targets.
When will Dholera airport open?
Not open as of 12 November 2026. The Chief Minister was told on 16 October 2026 that it is expected to be operational by the end of 2026. No licence or airline schedule has been reported.
When will the Tata fab in Dholera start production?
Commercial production is reported for mid-2028, according to the minister as reported by TrendForce on 20 July 2026. Some broker pages say December 2026, which conflicts with that and should not be relied on.
Is Dholera smart city ready?
Parts are built: the Activation Area has roads and utilities, and the expressway was inaugurated on 31 March 2026. The wider region is under development and the airport and fab are not yet complete.
How long will Dholera take to develop?
The sanctioned plan spans about 30 years in three phases, with the last phase running 2033 to 2042. Development of the region as a whole will take years more than any single project target suggests.
Read next
- Dholera milestones 2028 to 2042
- Masterplan by phase, ranked by area
- Best time to buy in Dholera
- Mega projects
- Refund and cancellation rights
Sources
- Final Development Plan for the Dholera SIR, DSIRDA (sanctioned 10 September 2012; extracted August 2026)
- Gujarat CM takes stock of projects in Dholera region, NewKerala (16 October 2026)
- Cabinet approves 134 km semi-high-speed rail line between Ahmedabad and Dholera, ThePrint (13 May 2026)
- Tata's India fab to launch at 90nm, production mid-2028, TrendForce (20 July 2026)