Bhimnath Dholera rail line: what is built, who builds it and the 2027 target
Updated 13 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.
The Bhimnath to Dholera line is a new broad gauge rail link, reported as 23 km, to connect Dholera SIR with the existing Ahmedabad to Bhavnagar line. The DICDL annual report for 2024-25 says Western Railways began construction in early 2025 and expects completion by early 2027. No source read on 13 November 2026 reports a newer date, a percentage built or a cost.
Bhimnath Dholera rail line, step by step from approval to the 2027 target
| When | What happened | Source |
|---|---|---|
| 21 September 2021 | NICDIT board approves a new rail line from Bhimnath to Dholera SIR on the Non-Government Railway model, to be built by a new company owned 50:50 by NICDIT and the Government of Gujarat | DICDL annual report 2024-25, note 36 |
| 1 November 2021 | DICDL board resolves that DICDL will carry the project's costs until the new company exists, to be reimbursed by it | DICDL annual report 2024-25, note 36 |
| By 31 March 2024 | Rs 358.46 lakh spent on the project and booked as a receivable; later received from the State Budget through DSIRDA | DICDL annual report 2024-25, note 36 |
| Not dated in the report | Railway Board decides the line will be built by the Zonal Railways under Railway funding, with land supplied by the Government of Gujarat; no new company is needed | DICDL annual report 2024-25, note 36 |
| Year to 31 March 2025 | DICDL spends a further Rs 28.07 lakh on the project, again received from the State Budget through DSIRDA | DICDL annual report 2024-25, note 36 |
| Early 2025 | Western Railways starts construction of a new broad gauge line connecting Dholera SIR to the existing Ahmedabad to Bhavnagar line | DICDL annual report 2024-25, page 21 |
| 16 October 2026 | Gujarat Chief Minister's review mentions a 23 km Bhimnath to Dholera logistics hub railway line as under development, separate from the 134 km semi-high-speed line | NewKerala report, 16 October 2026 |
| Early 2027 (target) | Completion anticipated by the 2024-25 annual report. No later source read for this page confirms or changes it | DICDL annual report 2024-25, page 21 |
Download this table (CSV). Last checked 13 November 2026. Free to quote with a link to this page.
What the line is for
The Bhimnath to Dholera line is meant to link the region to the existing Ahmedabad to Bhavnagar broad gauge route, so that goods can move to and from the SIR by rail. The October 2026 report calls it the Bhimnath to Dholera logistics hub line. It is a freight and logistics link first. It is not the Ahmedabad to Dholera semi-high-speed line, which is a separate 134 km project, and it is not a metro. Our Dholera timeline shows where each connection stands.
Who is building it and who pays
The plan changed after 2021. In September 2021 the NICDIT board approved the line to be built under the Non-Government Railway model by a joint company of NICDIT and the Government of Gujarat. Later the Railway Board decided that the Zonal Railways would execute the line under Railway funding, and that the State would provide the land. The annual report says this removed the need for a new company. DICDL had already spent Rs 358.46 lakh on early work to 31 March 2024, and the State Budget refunded it through DSIRDA. It spent Rs 28.07 lakh more in 2024-25, refunded the same way. One lakh is 100,000.
What the 2024-25 annual report says about construction
On page 21 the report says Western Railways has started building a new broad gauge line connecting Dholera SIR to the existing Ahmedabad to Bhavnagar line, that the project began in early 2025 and that completion is anticipated by early 2027. That is a target stated by the company, not an audited outcome. The report does not use the name Bhimnath on that page, so this page treats it as the same project because note 36 of the same report describes one rail line from Bhimnath to Dholera SIR and names no other new broad gauge line.
What has not been reported
The reports read for this page give no percentage of work done, no contractor, no cost and no track length from an official document. The 23 km figure comes from the 16 October 2026 news report. Anyone quoting a cost or an opening date for this line should show where it comes from. Related work on the corridor, such as the road and the airport, is covered in trunk infrastructure and roads and the mega projects page.
How it differs from the other Dholera rail lines
Three different lines are discussed in Gujarat reports. The Bhimnath to Dholera line is the 23 km broad gauge link above. The Ahmedabad to Dholera semi-high-speed line is described in the October 2026 report as a 134 km line linking Ahmedabad, Dholera SIR, the airport and Lothal. A Bhavnagar to Dholera rail line has also been reported separately. Each has its own approval and stage, and this page covers only the first.
Why the 2027 date should be read as a target
The same annual report gave earlier targets for other Dholera projects that later moved. The report's own wording is "anticipated", and railway projects in Gujarat depend on land handover and works by the Zonal Railways, not on DICDL. Treat early 2027 as the date the company expects, and check the Western Railway and Ministry of Railways pages for any change.
What this page cannot tell you
This page covers what DICDL's annual report and one dated news report say about the Bhimnath to Dholera line. It cannot tell you progress on site, cost, or an opening date, and it is not a guide to buying land near the line.
Questions people ask
How long is the Bhimnath to Dholera rail line?
The 16 October 2026 news report of the Chief Minister's review calls it a 23 km logistics hub line. The DICDL annual report does not give a length.
When will the Bhimnath to Dholera rail line be completed?
The DICDL annual report for 2024-25 says it is anticipated to be completed by early 2027, with construction by Western Railways starting in early 2025. This is a target, and no newer official date was found on 13 November 2026.
Who is building the Bhimnath to Dholera line?
The Zonal Railways under Railway funding. The annual report says the Railway Board took the project up, the State supplies the land and no separate company is being formed.
Is it the same as the Ahmedabad Dholera semi-high-speed rail?
No. The semi-high-speed line is a 134 km double line linking Ahmedabad, Dholera SIR, the airport and Lothal. The Bhimnath line is a separate 23 km broad gauge link.
How much has been spent on the Bhimnath Dholera line by DICDL?
Rs 358.46 lakh to 31 March 2024 and Rs 28.07 lakh in 2024-25. The State Budget reimbursed both through DSIRDA, so this is early work cost, not the cost of the line.
Read next
- Dholera timeline
- Dholera mega projects
- Trunk infrastructure and roads
- Logistics and warehousing in Dholera
- Delhi Mumbai Industrial Corridor nodes
Sources
- DICDL 9th Annual Report 2024-25, note 36 and page 21 (signed 22 August 2025)
- DICDL, annual reports list (nine reports, FY2016-17 to FY2024-25) (checked 13 November 2026)
- NewKerala, Gujarat CM takes stock of projects in Dholera region (16 October 2026)