Delhi Mumbai Industrial Corridor nodes: the nine projects and how far each has got, as on 31 May 2026
Updated 13 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.
The Government's status report on industrial corridors, as on 31 May 2026, lists nine Delhi Mumbai Industrial Corridor projects. Four report land allotted: Shendra-Bidkin in Maharashtra 3,434 acres, Vikram Udyogpuri in Madhya Pradesh 519, Dholera in Gujarat 504 and Greater Noida 316. The other five are logistics hubs or earlier-stage plans. Checked on 13 November 2026.
The nine DMIC projects in the 31 May 2026 status report
| Project | State | Plots allotted | Acres allotted | What the report says about the stage |
|---|---|---|---|---|
| Shendra Bidkin Industrial Area (AURIC) | Maharashtra | 332 | 3,434 | Trunk infrastructure for Shendra largely complete; Bidkin Sector A (10.32 sq km) trunk works complete; anchor investor Hyosung (100 acres) |
| Integrated Industrial Township at Vikram Udyogpuri | Madhya Pradesh | 67 | 519 | Major trunk infrastructure complete; dedicated to the nation on 2 October 2023; anchor investor AMUL |
| Dholera Special Investment Region | Gujarat | 12 | 504 | Phase 1 activation area of 22.5 sq km, trunk infrastructure complete; anchor investor Tata Chemicals; 1,083 acres of industrial land available |
| Integrated Industrial Township at Greater Noida | Uttar Pradesh | 31 | 316 | Major trunk infrastructure complete; IIT Greater Noida dedicated in January 2024; anchor investor Haier |
| Integrated Multimodal Logistics Hub at Nangal Chaudhary | Haryana | not stated | not stated | Internal rail works about 95 per cent complete; trial run expected in June 2026; PPP concessionaire bids due 30 June 2026 |
| Multi Modal Logistics Hub at Dadri and Transport Hub at Boraki | Uttar Pradesh | not stated | not stated | Approved 30 December 2020; 562 of 1,183 acres transferred to the project company |
| Jodhpur Pali Marwar Industrial Area | Rajasthan | not stated | not stated | Consultants appointed for master planning; state proposes a revised 8,121 acres in 3 phases |
| Khushkheda Bhiwadi Neemrana Investment Region | Rajasthan | not stated | not stated | Consultants appointed for master planning on 558 hectares; Development Plan notified as an SIR on 12 October 2020 |
| Dighi Port Industrial Area | Maharashtra | not stated | not stated | 6,056 acres confirmed in January 2021; Cabinet Committee approval received 28 August 2024 |
Download this table (CSV). Last checked 13 November 2026. Free to quote with a link to this page.
Shendra-Bidkin has allotted far more land than the other three projects that report a figure.
What the DMIC is
The Delhi Mumbai Industrial Corridor was the first industrial corridor project the Government of India announced, with projects approved in 2014 and 2015. The status report says the Western Dedicated Freight Corridor was taken as its transport backbone. The corridor is run by the National Industrial Corridor Development Corporation, known as NICDC. Dholera, in the report's numbering, is project 1.1.
How the report counts progress
The report records land allotted to companies, trunk infrastructure completed, plots still available and the approval stage for nodes not yet built. Four of the nine projects state how much land has been allotted. Two are logistics hubs with their own rail and terminal works, and three are earlier-stage nodes where consultants are still preparing master plans. The stages are different, so a total of acres across all nine would mean nothing.
Where Dholera stands on the figures
The report says 12 plots of 504 acres have been allotted at Dholera, of which 436 acres are industrial, with Tata Chemicals as the anchor investor. It adds that 1,083 acres of industrial land and 1,032 acres of commercial, residential and other land are ready for allotment. State government land transferred to DICDL stands at 48.31 sq km. The solar park figure it gives is 300 MW commissioned out of 1,000 MW. See our page on how big Dholera SIR is for how that compares with the whole 920 sq km plan.
A line in the report that is out of date
The report says the 6-lane Ahmedabad to Dholera expressway is being implemented by NHAI. Other records on this site show that the expressway was inaugurated on 31 March 2026, so this wording is likely carried over from earlier reports. We keep the expressway date from our own records, and we flag the difference for anyone comparing the two documents. The airport entry says construction works are underway, which matches our record that the airport is not open.
Plans that are still plans
Jodhpur Pali Marwar, Khushkheda Bhiwadi Neemrana and Dighi Port are described in terms of consultants, land confirmed by the state and approvals, not allotments. They are plans. Our milestones page labels Dholera's own long-range dates the same way.
Comparing Dholera with the others
Allotment per project is not a ranking of quality. Shendra-Bidkin started allotting earlier, with its first AURIC hall dedicated in September 2019. Vikram Udyogpuri was dedicated to the nation in October 2023 and has 67 plots. Dholera's 12 plots cover 504 acres, which means its plots are larger on average than those at Vikram Udyogpuri, going by the report's own totals (about 42 acres a plot against about 8 acres, our division of the report's figures).
What to watch in the next report
The next status report will show whether Dholera's allotted acres rise from 504, whether the industrial land available stays at 1,083 acres, and whether the expressway wording is corrected. We follow the same quantities on our completion date page.
What this page cannot tell you
This page reads one status report dated 31 May 2026. The figures were reported by the corridor company and have not been audited by us. The report does not say what share of each node's total land has been sold, so allotment cannot be turned into a percentage.
Questions people ask
Which are the Delhi Mumbai Industrial Corridor nodes?
The 31 May 2026 status report lists nine projects: Dholera in Gujarat, Shendra-Bidkin and Dighi Port in Maharashtra, Greater Noida, Vikram Udyogpuri, two logistics hubs, Jodhpur-Pali-Marwar and Khushkheda-Bhiwadi-Neemrana.
How much land has been allotted at Dholera?
The report says 12 plots of 504 acres have been allotted at Dholera, 436 acres of them industrial, with Tata Chemicals as the anchor investor, and 1,083 acres of industrial land remain available.
Which DMIC node has allotted the most land?
Shendra-Bidkin in Maharashtra, with 332 plots of 3,434 acres allotted per the report. Vikram Udyogpuri has 519 acres, Dholera 504 and Greater Noida 316.
Is Dholera part of the Delhi Mumbai Industrial Corridor?
Yes. The NICDC status report lists the Dholera Special Investment Region as project 1.1 of the DMIC. It was planned over about 920 sq km, with a Phase 1 activation area of 22.5 sq km.
What is NICDC?
The National Industrial Corridor Development Corporation, the central company that develops industrial corridor projects, including the DMIC. Its status is reported to the Delivery Monitoring Unit of the Department for Promotion of Industry and Internal Trade.
Does the report say the Dholera airport is open?
No. It says the greenfield international airport is being implemented by Dholera International Airport Company Limited and that construction works are underway. Other records on this site show it is not yet open.
Read next
- How big is Dholera SIR
- Dholera milestones on the road to 2047
- Dholera smart city completion date
- Dholera timeline
- Viksit Gujarat 2047 targets
Sources
- DPIIT: National Industrial Corridor Development Corporation, status of industrial corridor projects (Delivery Monitoring Unit proforma), as on 31 May 2026 (as on 31 May 2026; opened 13 November 2026)
- PIB: Travelling Across the Industrial Corridors of India (26 February 2026)
- DPIIT: Status of Industrial Corridor Projects (December 2025 edition) (December 2025)