Dholera timeline: the key dated events from the 2009 notification to November 2026

Updated 11 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.

The Dholera timeline starts with the SIR notification of 22 May 2009. The Final Development Plan was sanctioned in 2012 and the city company was formed on 28 January 2016. Trunk infrastructure in the 22.5 sq km Activation Area was reported complete in August 2025, and the expressway was reported inaugurated on 31 March 2026. The airport is not open. Checked on 13 November 2026.

Eighteen dated events, oldest first

No.DateWhat happenedSourceKind
122 May 2009Industries and Mines Department notification declares the Dholera Special Investment Region. The 22 villages in it add up to 879.34 sq kmGujarat Government Gazette, 4 June 2009Official
210 September 2012Apex Authority (GIDB) sanctions the Final Development Plan, DSIRDA Report 1Final Development PlanOfficial
33 October 2012Apex Authority notification sanctions draft Town Planning Scheme 1, published in the Gazette on 11 October 2012Gazette Extraordinary, Extra No. 323Official
424 October 2013Apex Authority notification sanctions draft Town Planning Scheme 3Notification SIRAA/06/2013/439Official
519 September 2014Environmental clearance granted by the Ministry of Environment, Forest and Climate ChangeNICDC Delivery Monitoring Unit report, 30 June 2026Official
62015Gujarat High Court stays the land acquisition after farmer petitions; a 2017 press report found about 290 of 900 sq km secured by thenBusiness Standard, 2017Reported
728 January 2016DICDL, the company that builds the city, is incorporatedNICDC Delivery Monitoring Unit report, 30 June 2026Official
821 September 2021Bhimnath to Dholera rail line approved by the NICDIT Board of TrusteesNICDC Delivery Monitoring Unit report, 30 June 2026Official
910 July 2023Foxconn withdraws from its joint venture with Vedanta, which had signed a memorandum with Gujarat in September 2022; no plant was builtBusiness Standard, July 2023Reported
1029 February 2024Union Cabinet approves the Tata Electronics fab at Dholera under the India Semiconductor Mission, about Rs 91,000 crorePIB release (PRID 2108602)Official
1130 June to 31 August 2025The monthly report's wording on Activation Area trunk infrastructure changes from 'nearing completion' to 'complete'NICDC Delivery Monitoring Unit reportsOfficial
1229 July 2025A Lok Sabha reply lists Dholera SIR among four completed projects of the national industrial corridor programmeLok Sabha Unstarred Question 1421Official
1331 March 2026Ahmedabad Dholera expressway reported inauguratedNews reportsReported
1413 May 2026Union Cabinet approves the 134 km Ahmedabad to Dholera semi-high-speed rail, about Rs 20,667 crore, completion up to 2030-31PIB release (PRID 2260624)Official
154 June 2026First trial landing at Dholera airport by an AAI aircraftNews reportsReported
1617 September 2026Fujifilm and Tata Electronics sign a strategic memorandum; Fujifilm plans about Rs 800 crore in phases for a materials plant in the SIRFujifilm press releaseOfficial
1716 October 2026At a review, the Chief Minister is told the airport is expected to be operational by the end of 2026News wire reportReported
18About 4 November 2026AAI signs an operation and maintenance agreement with DIACL for Dholera airport; no opening date is givenIndian Masterminds; CAPAReported

Official rows come from a government gazette, notification, release or report. Reported rows are from news outlets and are labelled as reported. Where a date is not in the record we print the period or the year only.

Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.

How to read the timeline

Each row gives a date, the event, the source and a label. Official means a government gazette, notification, press release or monitoring report. Reported means a news outlet, and we say so. A date that the record does not give is printed as a year or a period and not guessed. The table is a record of what happened and when, and it is not a forecast. For the dates that lie ahead, see our page on the milestones from 2028 to 2042.

2009 to 2016: the legal and planning foundation

The region was declared by a notification of 22 May 2009, published in the Gazette on 4 June 2009, under the Gujarat Special Investment Region Act of 2009. The 22 villages named in it add up to 879.34 sq km, and our village area table lists each. The Final Development Plan followed on 10 September 2012, and draft town planning schemes 1 and 3 were sanctioned in October 2012 and October 2013, which is the structure explained in our town planning schemes page. The environmental clearance is dated 19 September 2014, and the city company, DICDL, was incorporated on 28 January 2016. A 2017 press report found only about 290 of more than 900 sq km of land secured, after the High Court stay on acquisition in 2015.

2017 to 2023: approvals and one collapsed proposal

The record for these years has fewer dated works. The rail line from Bhimnath to Dholera was approved by the NICDIT Board on 21 September 2021. A Vedanta and Foxconn memorandum with Gujarat, signed in September 2022 and often quoted at about US$19.5 billion, ended when Foxconn withdrew on 10 July 2023. No plant was built under it, and we do not treat that figure as committed capital.

2024 to 2026: the fab, the roads and the airport

The Union Cabinet approved the Tata Electronics fab on 29 February 2024 at about Rs 91,000 crore. Over 2025 the monthly government report moved from saying Activation Area trunk infrastructure was nearing completion to saying it was complete. In 2026 the record is dense: the expressway was reported inaugurated on 31 March, the semi-high-speed rail was approved on 13 May, the airport had its first trial landing on 4 June, and the Fujifilm and Tata Electronics memorandum was signed on 17 September. On 16 October the Chief Minister was told the airport should be operational by the end of 2026, and an operation and maintenance agreement for it was reported around 4 November. The airport is not open, and no licence or airline schedule has been reported.

Dates still ahead

Three dated targets sit after the last row of the table, and all are plans and not completed events. The Chief Minister was told on 16 October 2026 that the airport should be operational by the end of 2026 (NewKerala report). The Union Cabinet release of 13 May 2026 says the semi-high-speed rail will be completed up to 2030-31 (PIB). Commercial production at the Tata fab is reported for mid-2028 by Bloomberg through TrendForce, dated 20 July 2026, which also reported that the fab may launch mostly on 90 nm processes while the company says it will span 28 to 110 nm. Targets move, so treat each one as the latest stated plan.

How long things took

From the notification of 22 May 2009 to the monthly report of 31 August 2025 that called Activation Area trunk infrastructure complete is about 16 years. That area is 22.5 sq km of the planned 920 sq km, so about 2.4 per cent of the region by area. The city company took about 6 years and 8 months to be formed after the notification. These are intervals between dated entries in the table. They are not measures of whether the project is early or late, because the record does not give one fixed schedule that all of these dates were measured against.

What the record cannot date

Several things people ask about have no reliable date in the record. The date of any calibration flight at the airport is not given in the reports we hold. The Tata fab's percentage complete is quoted by blogs but not by a government or company source, so we print none. The date at which the full 920 sq km will be built is not stated anywhere. The sanctioned plan lists Phase II for 2023 to 2032 and Phase III for 2033 to 2042, and our phase area page explains those periods. See also our page on the smart city completion date.

What this page cannot tell you

This page cannot tell you when any future work will be finished, and it is not a complete list of every event at Dholera. It holds the dated events that a gazette, a notification, a government release, a government report or a named news outlet supports.

Questions people ask

When was Dholera SIR declared?

By a notification of the Industries and Mines Department dated 22 May 2009, published in the Gujarat Government Gazette on 4 June 2009. It is based on the Gujarat Special Investment Region Act 2009, and it named 22 villages.

When was the Dholera city company formed?

DICDL, the Dholera Industrial City Development Limited, was incorporated on 28 January 2016, according to the NICDC monitoring report as on 30 June 2026. It is the company that builds the city's trunk infrastructure.

When did Dholera infrastructure get completed?

The monthly government report said trunk infrastructure in the 22.5 sq km Phase I Activation Area was nearing completion on 30 June 2025 and complete on 31 August 2025. That is the only transition recorded, and it covers the Activation Area, not the whole 920 sq km.

When was the Tata semiconductor fab approved?

The Union Cabinet approved it on 29 February 2024 under the India Semiconductor Mission, at about Rs 91,000 crore. Commercial production has been reported for mid-2028, which is a target.

When did the Ahmedabad Dholera expressway open?

It was reported inaugurated on 31 March 2026. The monthly government report for 30 June 2026 still describes it as being implemented by NHAI, so check the highways authority notice before you plan a journey.

Has the Dholera airport opened?

No. A first trial landing took place on 4 June 2026, and on 16 October 2026 the Chief Minister was told it is expected to be operational by the end of 2026. No licence or airline schedule had been reported by 11 November 2026.

Read next

Sources

  1. Gujarat Government Gazette, Part IV-B, 4 June 2009: notification declaring the Dholera SIR (22 May 2009). The gazette copy itself was not found online; the Dholera portal confirms the region and the SIR Act (checked 13 November 2026)
  2. DSIRDA: Final Development Plan page and DP Report 1 (sanctioned 10 September 2012) (checked 13 November 2026)
  3. DSIRDA: Draft Town Planning Scheme No.1 notification and plan (checked 13 November 2026)
  4. DSIRDA: Draft Town Planning Scheme No.3 notification and plan (checked 13 November 2026)
  5. NICDC and DPIIT Delivery Monitoring Unit report, Dholera section (version on the NICDC site, as on 30 September 2026; it repeats the dates of 19 September 2014, 28 January 2016 and 21 September 2021) (30 September 2026)
  6. PIB: Union Cabinet approves three more semiconductor units, including the Tata fab at Dholera (29 February 2024)
  7. PIB: Cabinet approves the Ahmedabad to Dholera semi-high-speed rail, Rs 20,667 crore (13 May 2026)
  8. Fujifilm: strategic partnership with Tata Electronics (17 September 2026)
  9. Indian Masterminds and CAPA: AAI and DIACL operation and maintenance agreement for Dholera airport (about 4 November 2026)