Industrial corridors in India: the 11 corridor projects, the road or rail line each follows, and where each stands

Updated 13 November 2026. Compiled by the Dholera 2047 desk from the sources listed at the end of this page.

The Government's status report as on 31 May 2026 covers 11 industrial corridor projects. PIB says projects across them are under implementation, with 4 completed and 4 nearing completion as of February 2026. The Delhi Mumbai corridor, which includes Dholera, has nine named projects, the most of any corridor. Several corridors are still at the planning stage. Checked on 13 November 2026.

The 11 corridors in the Government's order

No.CorridorBackbone it followsProjects or nodes named in the reportStage in the 31 May 2026 report
1Delhi Mumbai Industrial Corridor (DMIC)Western Dedicated Freight Corridor9First corridor announced; Dholera, Vikram Udyogpuri, Shendra-Bidkin and Greater Noida have land allotted
2Amritsar Kolkata Industrial CorridorEastern Dedicated Freight Corridor, 1,839 km in six states7Manufacturing clusters at Khurpia and Rajpura-Patiala have EPC contracts; the Jharkhand site is unavailable
3East Coast Industrial Corridor (Vizag Chennai, Phase 1)NH 163Kopparthy has an EPC contract; Chittoor and the Nakapalli cluster land is not being pursued under the Government framework
4Chennai Bengaluru Industrial CorridorBangalore Chennai Expressway (NE-7)2Krishnapatnam foundation stone laid on 8 January 2025; Tamil Nadu asked to look for alternate sites
5Extension of CBIC to Kochi via CoimbatoreNH 5441Palakkad: 889 acres transferred; EPC letter of award on 24 September 2025
6Bengaluru Mumbai Industrial CorridorNH 482Dharwad and Satara nodes: consultants appointed; land status awaited from the states
7Hyderabad Bengaluru Industrial CorridorNH 441Orvakal: foundation stone laid on 16 October 2025; EPC kick-off in December 2025
8Hyderabad Nagpur Industrial CorridorNH 441Zaheerabad: foundation stone laid on 10 May 2026
9Hyderabad Warangal Industrial CorridorNH 1630No project named in the report
10Odisha Economic CorridorNH 162Further development on hold because land parcels are not confirmed
11Delhi Nagpur Industrial CorridorNH 44 and the future North-South freight corridor0Draft perspective plan circulated to the states

Download this table (CSV). Last checked 13 November 2026. Free to quote with a link to this page.

Number of projects or nodes named under each corridor in the DPIIT report as on 31 May 2026
Delhi Mumbai Industrial Corridor (DMIC)9
Amritsar Kolkata Industrial Corridor7
East Coast Industrial Corridor (Vizag Chennai, Phase 1)3
Chennai Bengaluru Industrial Corridor2
Bengaluru Mumbai Industrial Corridor2
Odisha Economic Corridor2
Extension of CBIC to Kochi via Coimbatore1
Hyderabad Bengaluru Industrial Corridor1
Hyderabad Nagpur Industrial Corridor1

The Delhi Mumbai corridor has the most named projects, and two corridors have none yet.

How many industrial corridors does India have?

Eleven corridor projects appear in the National Industrial Corridor Development Corporation's status report to the Delivery Monitoring Unit of the Department for Promotion of Industry and Internal Trade, as on 31 May 2026. PIB's feature of 26 February 2026 gives the same count and says that, across the 11 corridors, 4 projects have been completed and 4 are nearing completion. The count is of corridors, which are long strips of planned development. Each corridor holds several nodes or industrial areas.

What a corridor is

PIB describes an industrial corridor as a linear development zone connecting major economic centres through roads, railways, ports and airports, with the aim of faster industrial growth and plug-and-play infrastructure. Each corridor in the report follows a transport backbone, a freight line or a national highway, which the third column shows. Our page on Viksit Gujarat 2047 shows how Gujarat links the same idea to logistics corridors and port cities.

Where Dholera fits

Dholera is project 1.1 in the Delhi Mumbai corridor, the first corridor announced and the one with the most named projects. The report records 12 plots of 504 acres allotted there. Our DMIC nodes page compares it with the other eight projects of that corridor.

Approvals and stages

The report notes that the Cabinet Committee on Economic Affairs gave its approval on 28 August 2024 for several nodes, among them Khurpia, Rajpura-Patiala, Kopparthy, Orvakal, Zaheerabad, Palakkad and Dighi Port. That date is the point where those nodes move from planning into building. The report then lists the later steps: a programme manager appointed, an EPC contractor selected, a foundation stone laid and a kick-off meeting held. Nodes at the consultant stage have not yet reached the contractor step.

Corridors that have stalled or are early

The Odisha Economic Corridor is on hold because the state has not confirmed land parcels. Hyderabad Warangal has no named project, and Delhi Nagpur has a draft perspective plan only. Some nodes under the East Coast corridor, at Chittoor and Nakapalli, are not being pursued under the Government framework because the land first identified is not going forward. These items are plans or pauses, and we do not count them as built.

What was announced in the 2026 Budget

PIB's February 2026 feature says the Union Budget 2026 to 2027 announced an integrated East Coast Industrial Corridor with a connected node at Durgapur, and allotted Rs 3,000 crore to the National Industrial Corridor Development and Implementation Trust. Both are announcements of intent. No node date for Durgapur is given.

How to read this for 2047

Industrial corridors are long-range projects whose first nodes took more than a decade from announcement to allotment. Our Dholera timeline shows the same gap for Dholera itself, from the 2009 Act to the plots now allotted. For a planning view of the next ten years, treat each node's stage in this table as the best guide, and treat the stated corridor goals as targets.

What this page cannot tell you

This page counts the projects named in one status report. It cannot tell you how much land each node will eventually hold, when any node will open, or how many jobs a corridor will create. Stage descriptions are condensed from the report and may omit detail.

Questions people ask

How many industrial corridors are there in India?

The Government's status report as on 31 May 2026 covers 11 industrial corridor projects. PIB's February 2026 feature also counts 11, with 4 projects completed and 4 nearing completion.

Which industrial corridor is Dholera in?

The Delhi Mumbai Industrial Corridor. The status report lists the Dholera Special Investment Region as project 1.1 of its nine DMIC projects.

Which was the first industrial corridor project in India?

The Delhi Mumbai Industrial Corridor. The report says it was the first industrial corridor project announced, with projects approved by the Government of India in 2014 and 2015.

What is the backbone of the Delhi Mumbai Industrial Corridor?

The Western Dedicated Freight Corridor, according to the status report. The freight corridor's builder says it completed the whole Western line in March 2026.

Is the Odisha Economic Corridor going ahead?

Not at present. The report says further development is on hold because land parcels at the priority nodes are not confirmed.

What did the 2026 Budget say about industrial corridors?

PIB says it announced an integrated East Coast Industrial Corridor with a node at Durgapur, and Rs 3,000 crore for the National Industrial Corridor Development and Implementation Trust.

Read next

Sources

  1. DPIIT: National Industrial Corridor Development Corporation, status of industrial corridor projects, as on 31 May 2026 (as on 31 May 2026; opened 13 November 2026)
  2. PIB: Travelling Across the Industrial Corridors of India (explainer with the 11-corridor count and Budget 2026-27 items) (26 February 2026; opened 13 November 2026)
  3. DPIIT: Status of Industrial Corridor Projects (December 2025 edition) (December 2025; opened 13 November 2026)